April reminder and update on feasibility study:
- April 7 and 8th we are surveying the ditch by drone flight to get ortho imagery for base mapping.
- I will reach out to well owners we feel will give us the best data next week and set a date and time to go over our monitoring program at each well. We will begin the monitoring prior to ditch turn on.
- The first week of May up our engineer will be surveying the ditch by land. We will access the ditch at each road crossing and walk the length of the ditch.
- As we move forward in the study I will update this email list monthly. Please reach out to me at camden@methowsalmon.org, or 509.341.4133 with any questions.